Using Earned Value to Predict Your Project’s Success
This Post examines how the data points of Planned Value (PV), Earned Value (EV), and Actual Cost (AC) can be used to analyze the current status of a project and forecast its likely future. EVM looks at project performance for the current period and at cumulative performance to date. EVM is described and illustrated here in terms of cumulative data, using the Project data.
This post introduces a fourth data point, Budget at Completion (BAC), which is the final data point on the performance measurement baseline (PMB). Budget at Completion represents the total Planned Value for the project. For Project EZ, the BAC is 150.
This is a goof rule of thumb:
• If your SV >0 and your SPI > 1.0, you are ahead of schedule and under budget. If your SV = 0 and your SPI > 1.0, you are on budget and ahead of schedule. If your SV < 0 and your SPI 0 and your SPI > 1.0, you are ahead of schedule and under budget. If your SV = 0 and your SPI > 1.0, you are on budget and ahead of schedule. If your SV < 0 and your SPI < 1.0 you are behind in budget and schedule.
• Indices: Schedule Performance Index (SPI); Cost Performance Index (CPI); and To-Complete Performance Index (TCPI)
• Forecasts: Time Estimate at Completion (EACt); Estimate at Completion (EAC); and Estimate to Complete (ETC)
These variances, indices, and forecasts can be used to answer the key project management questions. It lets us show the relationship between those project management questions and the EVM performance measures.
Schedule Variance (Are we ahead or behind schedule?)
The Schedule Variance (SV) determines whether a project is ahead of or behind schedule. It is calculated by subtracting the Planned Value (PV) from the Earned Value (EV). A positive value indicates a favorable condition and a negative value indicates an unfavorable condition.
The Schedule Variance can be expressed as a percentage by dividing the Schedule Variance (SV) by the Planned Value (PV). In other words, the project is 33 percent behind schedule, meaning that 33 percent of the planned work has not been accomplished.
Schedule Performance Index (How efficiently are we using time?)
The Schedule Performance Index (SPI) indicates how efficiently the project team is using its time. SPI is calculated by dividing the Earned Value (EV) by the Planned Value (PV). The Schedule Performance Index indicates that—on average—for each 8-hour day worked on the project, only 5 hours and 20 minutes worth of the planned work is being performed; that is, work is being accomplished at 67 percent efficiency. This is a very useful statistic to use in resource allocation.
Time Estimate at Completion (When are we likely to finish work?)
Using the Schedule Performance Index (SPI) and the average Planned Value (PV) per unit of time, the project team can generate a rough estimate of when the project will be completed, if current trends continue, compared to when it was originally supposed to be completed.
The originally estimated completion time for the project was 12 months, so the project manager now knows that if work continues at the current rate the project will take six months longer than originally planned. It is important to note that this method generates a fairly rough estimate and must always be compared with the status reflected by a time-based schedule method such as critical path method. It is possible that an earned value analysis could show no schedule variance and yet the project is still behind schedule; for example, when tasks that are planned to be completed in the future are performed ahead of tasks on the critical path.
One trick I always use is to have the engineers update their time on the project daily. This is quite normal. But I also have them update the remaining time that task will take. If the original estimate was 40 hours, and the engineer spent 20 hours on it, that does not mean he is 50% done. Software is very hard to predict and new things are learned as one gets deeper in the project. So if the culture allows the engineers to update their remaining work every day, I can run Project scenarios to see if the critical path has changed. I can also have a discussion with the engineer to see if we can work smarter to pull in the estimate. Most of the time, we don’t spend enough time estimating a project and just jump in and write code. This mode usually bites you in the end.
Next I will show an example I found using the techniques I’ve written about in this post.

4 Comments »
Leave a comment
-
Archives
- June 2009 (2)
- May 2009 (4)
- April 2009 (1)
- March 2009 (1)
- January 2009 (3)
- December 2008 (6)
- November 2008 (7)
- October 2008 (16)
- September 2008 (24)
-
Categories
- Business Analyst
- Communications Management
- earned value
- Family
- friends
- Glossary
- Hurricanes
- Jesus
- knowledge areas
- Living Your Best Life
- Outsourcing
- Performance Management
- Phase Review Process
- PMBOK
- PMI
- PMO
- PMP
- Project Initiation
- Project Management
- Project Phases
- quality management
- Risk Management
- Schedule Management
- Scope Management
- Training
- Uncategorized
- Writing and Documentaiton
- Young Life
-
RSS
Entries RSS
Comments RSS
Thanks for this useful resource! Your explanations are clear. I confirm that EVM is a powerful project management tool!
Thanks for the kind words!
Donna,
To comment or not to comment? Edit and/or Post as you wish.
I hope you don’t mind if I propose a slightly different position on EV.
I am not so enthusiastic about it.
It’s good and useful up to a point, but has limitations, some of which you have mentioned. It should not be credited with super powers or voodoo magic that it doesn’t have.
EV is not predictive. It is all about the history.
BCWP and BCWS come straight out of a Baseline, and that Baseline becomes progressively out of date and obsolete as the project proceeds. Whatever prediction EV can be used for is limited to simple extrapolations, usually long range extrapolations based on limited short term historical data. It ignores the existence of a project plan which can (maybe) be changed to prevent the train wreck. Experience has shown that early EV numbers, the SPI and CPI, are very sticky and hard to shake off, so to this extent EV can be said to be good at predicting itself.
As you mention, Tasks done early are not rewarded with good EV scores. Also, EV rewards doing the wrong Tasks, such as being successful on non-critical Tasks but letting the critical Tasks slide.
When the individual EV numbers for a number of individual Tasks are amalgamated into a couple of numbers which are supposed to represent the overall performance on the whole project, it’s, well, meaningless.
EV provides no guidance as to the causes of the EV scores, and no guidance as to the possible options available to the PM to stay on course or get back on course.
On a slightly different topic, I would suggest that controlling the schedule is essentially all about the Start Date, Finish Date, Actual Duration and Remaining Duration. So I ask my engineers for the Actual Start, Actual Duration, and an estimate of Remaining Duration. Only then, how much Remaining Work. You can’t update the plan just by knowing that there is 10 Hours of Remaining Work. You need to know also that there is, say, 5 Days Remaining Duration, which might have been revised from, say, 2 Days.
The most common circumstance is that say PV=1000, and because whatever reasons, we can not start. So EV=0, SPI=0, how can we forcast the duration? Thanks!