Project Management

Change Mangement Items to Add to Project Plan

1      Project Change Management Plan

1.1   Change Management Approach

Every project experiences change. If change is not formally managed, there is little likelihood that a project will be completed on time and within budget. Change can affect a project’s scope, cost, quality, risk, schedule, and work products, as well as the functioning of the project team.

The IT Monitoring & Enterprise Alert – Recommend Architecture & Tools Project will adopt a collaborative change management approach emphasizing an understanding and agreement among all parties about what the project changes are and how they will be managed.

When the project team needs to determine whether there is a change, the baseline documents are always the reference point. The baseline document for this phase of the project will be this document, the “Project Definition” document. Anything that is not covered in the baseline or that alters the baseline is a change. The process allows for change during the project life cycle, but puts the change in the context of the latest documented agreement.

1.2   Types of Change

Change will be classified as either design change or non-discretionary change. Non-discretionary change results from a failure of someone to do what he/she previously committed to, or the failure of some previously planned event to occur, and is sometimes tracked as lost time. A design change is an enhancement/correction to the system after initial specifications have been approved.

1.3   Change Budget

The purpose of the change budget is to provide an appropriation (of dollars and/or hours) that a project can draw from when change is encountered. The Project Team manages the change budget, providing approval for change expenditures when a change is approved or denying change expenditures when a change is deferred or rejected.

1.4   Change Management Process

The project team will manage changes by using the process described in this subsection.

1.4.1 Submit Change Request

Any team member may submit a written change request to the Project Manager.  

1.4.2 Perform a Preliminary Evaluation

The Project Manager reviews each change request and determines whether to defer, reject, or accept the change. If the change is accepted, the Project Manager estimates the effort to perform the impact analysis. Because an impact analysis of significant effort can cause a change to the current project schedule and/or budget, the client must decide whether to move to impact analysis.

1.4.3 Analyze Impact

If the change is to undergo an impact analysis, the Project Manager will assign the change request to a project team member. For our project, simple technical implementation, the technical team assumes responsibility for the impact analysis and involves additional technical staff as necessary.

The assigned resource(s) and the Project Manager first review the estimate for the effort of the impact analysis, and then work together to determine the effort, cost, schedule, and resources needed to implement the proposed change.

1.4.4 Review and Implement the Change

The Project Manager submits the impact analysis report to Project Sponsors for review.

¨       If the change is approved, the appropriate processes are followed to update the work plan, project documents, and the change is implemented. 

¨       If the change is rejected, the Project Manager logs the decision and reason and closes the change request.

¨       If the change is deferred, the date for the next review is set.

1.5   Roles for Change Management

Role (Contact Name) Role
Project Manager Receives change requests
Project Core Team Performs preliminary evaluation
Project Sponsors Final authority to approve a change for implementation

August 28, 2009 - Posted by | PMP, Project Initiation, Scope Management

2 Comments »

  1. do you think the sponsor should hold the change budget instead of the sponsor? This would mean the budget was used for real changes not just cost overruns.

    Comment by Paul naybour | March 30, 2010 | Reply

    • You said sponser twice so I’m not sure what you mean. I think the Project Manager should own the change management budget and the sponsor should own the management budget (which is used for unforseen cost overruns).

      Donna

      Comment by Donna Ritter | March 31, 2010 | Reply


Leave a comment